Procurement · Technical Award Process

Tendering for Recycling and Sorting Facilities

Experts4Recycling translates the plant concept into clear technical tender documents. We structure the scope of work and interfaces, develop suitable qualification and award criteria, and support bidder queries, bid evaluation and the award decision.

Reviewed by our experts · Last updated: 16 November 2026

In short: Comparable bids only result when all bidders price the same functions, scope limits, interfaces and evidence requirements. A good tender reduces room for interpretation, makes deviations visible, and creates a traceable basis for decision-making.

What belongs in a technical tender?

The starting point is a sufficiently clear plant or functional concept. From this we develop a functional or a detailed technical specification, define the boundaries of supply and scope, and describe in particular capacity, input conditions, output requirements, availability, utilities, documentation, assembly, commissioning and performance tests.

Particular attention is paid to the interfaces between mechanical engineering, conveying technology, steel structures, construction, EICA (electrical, instrumentation, control and automation) and the existing installation. Undefined interfaces frequently lead to claims, schedule problems, or scope that nobody later feels responsible for.

Private procurement or public tendering?

For private projects, the process can be flexibly adapted to the market, project size and negotiation strategy. For public contracting authorities, the requirements of the Austrian Federal Procurement Act 2018 (Bundesvergabegesetz) also apply. Experts4Recycling handles in particular the technical scope of work, technical qualification and award criteria, bidder queries and bid evaluation.

Procurement-law decisions and formal procedural steps are coordinated — depending on the assignment — with the responsible procurement office or specialised legal counsel. This keeps technical and legal responsibility clearly separated.

Qualification, award and bid comparison

Qualification criteria assess whether a company can generally carry out the contract. Award criteria, by contrast, serve to compare the bids of qualified bidders. Criteria, weighting, evidence and evaluation method must fit the subject matter of the contract and be described so that the later evaluation remains traceable.

In addition to price, factors such as energy demand, availability, sorting performance, maintenance concept, schedule and service can be relevant. What matters is not the number of criteria but their measurability and their actual relevance to project success.

Who we work for

Public contracting authorities

Municipalities, cities, utilities and public bodies that must tender services in compliance with procurement law, from needs assessment to contract award.

Companies and bidders

You want to bid in a public tender and need support with the bid, technical documentation and proof of suitability.

Project owners

Investors, developers and operators who want to structure complex procurements and steer them safely through the procurement procedure.

Further services in the procurement procedure

  • Market analysis and prior information notice
  • Publication, deadlines and bidder communication
  • Support through to contract award and signing
  • Review proceedings and support with objections

How we support the tendering process

  1. Delineate the subject matter of the contract: define lots, scope of work, interfaces and procurement strategy.
  2. Prepare the documents: develop the technical scope of work, drawings, data sheets and evidence requirements.
  3. Develop the criteria: define technical qualification and award criteria with an evaluation logic.
  4. Support the bidder phase: answer technical questions, prepare clarifications and any required corrections.
  5. Evaluate the bids: compare completeness, technical deviations, performance values and prices in a structured way.
  6. Document the decision: prepare an evaluation report, scoring matrix and technical award recommendation.

Your result

  • a clearly delineated and calculable scope of work,
  • technically comparable bids with identifiable deviations,
  • traceable criteria and a documented bid evaluation,
  • reduced interface and claims risk,
  • a solid technical basis for the award decision.

Experts4Recycling provides technical and project-related procurement expertise. A specific number of bidders, a specific price, or a legally unassailable procedure cannot be guaranteed.

Practice from our projects

Our experience covers private procurement as well as public tendering procedures. This includes functional specifications, technical qualification and award criteria, bidder queries, bid comparisons and award recommendations for the conversion of mechanical-biological waste treatment facilities and for new e-waste sorting technology.

Technology and project coordination

DI Thomas Baldt

Founder and Managing Director · Technical Procurement

Responsible for scopes of work, technical criteria, bid evaluation and negotiation from a plant-engineering perspective.

Elisabeth Baldt

Legal Associate & Project Coordinator

Supports the structured preparation of tender documents, deadlines, bidder communication and procedural documentation.

Frequently asked questions about tendering

When should tendering begin?
Once the objectives, scope limits and key planning basis are sufficiently clear. Tendering too early creates many assumptions; tendering too late puts the schedule at risk.
Functional or detailed technical specification?
A functional specification mainly defines the desired outcome and leaves freedom in the solution. A detailed technical specification prescribes the execution more strongly. Which form fits depends on the level of planning and the procurement strategy.
What is the difference between qualification and award criteria?
Qualification concerns the company’s ability to carry out the contract. Award criteria compare the bids of those bidders who are qualified.
Must the cheapest bidder receive the contract?
Not necessarily. Depending on the procedure, the contract can be awarded to the most economically advantageous tender, provided the criteria were clearly defined in advance.
How are technical deviations assessed?
Deviations are checked against mandatory requirements, guaranteed performance values and the evaluation matrix. Key points are clarified through bidder queries or clarification meetings.
Does Experts4Recycling also support public tenders?
Yes, particularly on the technical side. Procurement-law decisions are coordinated, depending on the project, with the procurement office or specialised legal counsel.

Prepare your tender in a structured way

Do you need comparable bids, clear technical criteria, or support with an ongoing procurement process?