Project Development · Investment Decision

Feasibility Study for Recycling and Sorting Facilities

Experts4Recycling examines whether, and under what conditions, a planned plant project is feasible technically, economically and at the intended location. The study brings together input and market analysis, process variants, cost framework, permitting questions and business case into a traceable basis for decision-making.

Reviewed by our experts · Last updated: 16 November 2026

In short: A feasibility study does not just answer “Is this possible?” but also “Under what assumptions is it worthwhile?”. It makes dependencies, data gaps and go/no-go criteria visible before major investments are committed.

When is a feasibility study worthwhile?

It is advisable for new recycling processes, location decisions, capacity expansions, retrofit projects, or entry into new material streams. It is especially important when input quality, sales markets, technology, permitting feasibility or the investment amount are still associated with uncertainty.

What questions are examined?

At the outset, we define the objective, the system boundaries and the decision criteria. We then examine the available input quantities and qualities, possible technologies and output pathways. Location, logistics, land, infrastructure and permitting-related conditions are considered to the level of detail required for the decision.

The economic assessment covers, depending on the assignment, CAPEX, OPEX, staffing, availability, revenues, disposal costs and financing. Sensitivities show which assumptions have the strongest influence on the business case. This avoids false precision and instead produces a solid range.

Comparing variants instead of jumping to a preferred solution

A good study does not merely describe a preferred solution. It compares realistic variants using consistent criteria, documents reasons for exclusion, and shows which additional data are needed for the next decision. A SWOT or weighted-scoring analysis can supplement this with qualitative aspects such as flexibility, supplier dependency and expandability.

How we prepare the feasibility study

  1. Define the objective and system boundaries: establish the decision, the variants and the required level of accuracy.
  2. Review the basis: record input streams, sales channels, location, infrastructure and legal conditions.
  3. Develop technical variants: compare processes, capacities, material streams and key plant components.
  4. Calculate economic viability: bring together CAPEX, OPEX, revenues and further assumptions in a business case.
  5. Assess risks and sensitivities: present critical influencing factors, data gaps and scenarios transparently.
  6. Derive a recommendation: define next steps, decision gates and any required deeper analysis.

Your result

  • a clear report with documented assumptions and data sources,
  • a traceable comparison of the realistic project variants,
  • a technical and economic framework for the investment decision,
  • an overview of key risks, sensitivities and open points,
  • a clear recommendation to continue, adjust or stop the project.

A feasibility study replaces neither detailed engineering nor official permits. Its informative value depends on the quality of the available market, material-stream and cost data; assumptions and uncertainties are therefore stated explicitly.

Practice from our projects

Experts4Recycling has prepared feasibility and general engineering studies for, among others, residual-waste and lightweight-packaging sorting with an annual throughput of around 280,000 tonnes, refuse-derived fuel processing with around 150,000 tonnes per year, and polymer and PET recycling projects.

Your contact

DI Thomas Baldt

Founder and Managing Director · Industrial engineer (TU Graz)

More than 20 years of experience in technical project development, investment appraisal and international plant engineering.

Frequently asked questions about feasibility studies

What must already be known before the project starts?
At minimum, the objective, the planned material stream, a rough capacity, and location assumptions. Missing data are included in the study as a work package or scenario.
What is the difference between a feasibility study and plant engineering?
The feasibility study evaluates variants and investment conditions. Plant engineering then makes the selected variant concrete in terms of process, layout and interfaces.
Does the study include a business case?
Yes, if agreed. The business case brings together investment, operating costs, revenues and key assumptions, supplemented by sensitivities.
Who needs a feasibility study?
Operators and project developers, as well as management, supervisory bodies, investors or banks who need a traceable basis for decision-making.
Can the study also reach a negative result?
Yes. A study must also be able to show that a project is not worthwhile under the examined assumptions, or should first be changed.
How accurate are costs and revenues?
This depends on the project stage and the available data. Ranges, price basis, sensitivities and excluded items are stated transparently.

Clarify feasibility before investing

Would you like a solid assessment of the technical variants and the business case for your project?